Chinese firm seeks revival of Kohala Hydropower Project

• Ahead of PM’s visit, company wants financial close deadline extended till Sept 2027

• Seeks clarity about law for land procurement in AJK

• $2.5bn Kohala project has been delayed by three years


ISLAMABAD: Days before Prime Minister Shehbaz Sharif is scheduled to arrive in Beijing for a key visit, a Chinese company has demanded the revival of a hydropower project that has been delayed for around three years.


The Chinese sponsors of the $2.5bn Kohala Hydro­power Project (KHPP) have raised a series of demands regarding the 1,124MW project planned to be built on River Jhelum in Azad Kashmir.


Pakistan has been trying to revive the project, along with the 700MW Azad Pattan Hydropower project — also planned to be built in Azad Kashmir — as renewable energy projects were a key part of the China-Pakistan Econo­mic Corridor (CPEC) and Islamabad’s long term plan to use indigenous resources for power generation.


The projects were delayed as China Export and Credit Insurance Cor­poration (Sino­sure) was reluctant to provide insurance cover to the project amid dues of over Rs550bn, to be paid by Pakistani power companies to Chinese independent power producers (IPPs).


Recently, Planning Minister Ahsan Iqbal and the PM Office intensified efforts to revive the project. During and on the sidelines of CPEC Joint Coordination Committee’s meeting, Pakistan got a positive response from the Chinese leadership, and Sinosure reportedly asked the two project sponsors to file fresh letters of intent for investment and insurance coverage.


Fresh demands


However, ahead of the PM’s visit, China Three Gorges Cor­po­ration (CTG) demanded that the letter of support (LoS) and financial close deadline be extended by three years to September 30, 2027, instead of 2024.


Liu Yonggangm, the CEO of Kohala Hydro Company — a subsidiary of CTG — has written to the managing director of Private Power Infra­structure Board demanding the previous bank guarantee be kept unchanged, instead of doubling it as required under the power policy and, waive the extension fee.


The letter issued on Friday said CTG welcomed the efforts to address critical issues relating to KHPP.


It claimed that KHPP was “fully geared to achieve financial closing in December 2018” and had executed the Engineering, Procure­ment, and Construction (EPC) Contract and the Engineer’s Contract and mobilised machinery to start the construction.


Chinese and local workers and engineers were on-site, and preliminary construction activities had commenced when the project was “unexpectedly halted by the Government of AJ&K due to environmental concerns wrongly associated with the Neelum-Jhelum Hydro Power Project,” the letter added.


Subsequently, it took more than three years to address the issues raised by the Azad Kashmir government, resulting in significant delays.


Most of the project’s key issues have been resolved and a series of agreements, like the tripartite power purchase agreement, implementation agreement and water use agreements, were signed in 2020 and 2021, the Chinese official said in the letter.


Due to the disruptions, “lender interest in the Kohala HPP waned, and China Export & Credit Insurance Corporation’s (Sinosure) interest in providing insurance to the lenders diminished”.


The letter disclosed that some previous potential investors had backed out, forcing the sponsors to seek new financing options.


Given that the project is situated in AJK, where there is “a notable disinterest among lenders”, the company required additional time to secure alternative funding sources.


Currently, the CTG is tasked with securing $2.5 billion in financing and obtaining insurance coverage from Sinosure, hence the push for a three-year extension.


Moreover, the Chinese side has also raised “several outstanding key issues, with technical, financial, and environmental implications,” which must be addressed before achieving financial closure.


It said the company needed 8,600 kanals of land for the project, of which 4,607 kanals had already been acquired under the Land Acquisition Act, 1894.


Since the AJK government notified a new Land Acquisition Act in 2020 and new rules in 2021, the letter sought confirmation that the remaining land for the project would be purchased under the old law.


It also complained that the Nepra had “not honoured ECC decisions related to Sewage Treat­ment Plants and foreign exchange Losses/Gains in excess of 7pc on delayed payment”.


The company said despite adverse macroeconomic conditions, it remai­ned “steadfastly committed to advancing the project”. Therefore, it demanded an extension in LoS and a financial closing deadline of Sept 2027.


Published in Dawn, June 1st, 2024


http://dlvr.it/T7gvG5

Comments

Popular posts from this blog

Sindh police chief takes notice over viral alleged aerial firing videos of DIG East’s son

Sindh Inspector General of Police (IGP) Ghulam Nabi Memon took notice after videos of aerial firing allegedly by the son of a high-ranking Karachi police official surfaced on Thursday. Videos shared on social media allegedly showed the son of Karachi East Deputy Inspector General of Police Azfar Mahesar firing a pistol and rifles into the air while travelling in a luxury car. In one such video, policemen were also purportedly visible. Footage of the alleged incidents went viral on social media. A statement issued today from the Sindh police said IGP Memon ordered an inquiry against the DIG East and directed Karachi’s additional IGP to carry out the investigation. The statement added that departmental action would be initiated upon the inquiry’s completion. It said the investigation would also probe whether the weapons used in the incident were officially issued or not. “No one will be allowed to spread fear and chaos like this,” IGP Memon vowed. Meanwhile, DIG Mahesar

Casualties feared in Dir clashes between FC, intruding militants: reports

LOWER DIR: Casualties are feared on both sides as militants from Afghanistan reportedly attacked Frontier Corps (FC) personnel at multiple locations at the Pak-Afghan border in Maidan area of Lower Dir district on Saturday, as per unconfirmed reports. According to local residents and official sources, there were reports of militants’ infiltration from the Afghan side via the Shahi border area at Lamotai Top, Suripao and Safarai forest. However, the reports were yet to be confirmed by Inter Services Public Relations, the military’s media wing. On getting information about the alleged infiltration, troops of the paramilitary force, FC, led by Captain Yasin, Captain Asfandiar and Subedar Hamza, advanced to block the militants’ movement, as per reports. The militants allegedly attacked the troops, who also retaliated, thus prompting fears of casualties on both sides. The security forces surrounded alleged militants at three different locations. Later, gunship helicopters lau

Family points finger at PPP MNA, two sons in journalist Nasrullah Gadani’s murder in Ghotki

SUKKUR: Slain journalist Nasrullah Gadani’s mother and two relatives have reiterated the allegation in statements recorded under Section 164 CrPC in a Mirpur Mathelo court that Pakistan Peoples Party’s MNA and his two sons had Nasrullah killed through their men. Ms Pathani Gadani, who was complainant in the case, and witnesses, Yaqoub Gadani and Salahuddin Gadani along with their counsel advocate Salahuddin Panhwar appeared before the second civil and first magistrate the other day and told him that PPP MNA Khalid Khan Loond, his sons, Shehbaz Loond, who was chairman of Mirpur Mathelo municipal committee, and Noor Mohammad Loond, had Nasrullah slain but the trio was so powerful that police had not dared include their names in the FIR. They appealed to the court to bring Nasrullah’s real killers to justice as per law and serve speedy justice to the bereaved family. Gadanis’ counsel Salahuddin Panhwar told media persons that the complainant and the witnesses had clearly stated t