Chinese firm seeks revival of Kohala Hydropower Project

• Ahead of PM’s visit, company wants financial close deadline extended till Sept 2027

• Seeks clarity about law for land procurement in AJK

• $2.5bn Kohala project has been delayed by three years


ISLAMABAD: Days before Prime Minister Shehbaz Sharif is scheduled to arrive in Beijing for a key visit, a Chinese company has demanded the revival of a hydropower project that has been delayed for around three years.


The Chinese sponsors of the $2.5bn Kohala Hydro­power Project (KHPP) have raised a series of demands regarding the 1,124MW project planned to be built on River Jhelum in Azad Kashmir.


Pakistan has been trying to revive the project, along with the 700MW Azad Pattan Hydropower project — also planned to be built in Azad Kashmir — as renewable energy projects were a key part of the China-Pakistan Econo­mic Corridor (CPEC) and Islamabad’s long term plan to use indigenous resources for power generation.


The projects were delayed as China Export and Credit Insurance Cor­poration (Sino­sure) was reluctant to provide insurance cover to the project amid dues of over Rs550bn, to be paid by Pakistani power companies to Chinese independent power producers (IPPs).


Recently, Planning Minister Ahsan Iqbal and the PM Office intensified efforts to revive the project. During and on the sidelines of CPEC Joint Coordination Committee’s meeting, Pakistan got a positive response from the Chinese leadership, and Sinosure reportedly asked the two project sponsors to file fresh letters of intent for investment and insurance coverage.


Fresh demands


However, ahead of the PM’s visit, China Three Gorges Cor­po­ration (CTG) demanded that the letter of support (LoS) and financial close deadline be extended by three years to September 30, 2027, instead of 2024.


Liu Yonggangm, the CEO of Kohala Hydro Company — a subsidiary of CTG — has written to the managing director of Private Power Infra­structure Board demanding the previous bank guarantee be kept unchanged, instead of doubling it as required under the power policy and, waive the extension fee.


The letter issued on Friday said CTG welcomed the efforts to address critical issues relating to KHPP.


It claimed that KHPP was “fully geared to achieve financial closing in December 2018” and had executed the Engineering, Procure­ment, and Construction (EPC) Contract and the Engineer’s Contract and mobilised machinery to start the construction.


Chinese and local workers and engineers were on-site, and preliminary construction activities had commenced when the project was “unexpectedly halted by the Government of AJ&K due to environmental concerns wrongly associated with the Neelum-Jhelum Hydro Power Project,” the letter added.


Subsequently, it took more than three years to address the issues raised by the Azad Kashmir government, resulting in significant delays.


Most of the project’s key issues have been resolved and a series of agreements, like the tripartite power purchase agreement, implementation agreement and water use agreements, were signed in 2020 and 2021, the Chinese official said in the letter.


Due to the disruptions, “lender interest in the Kohala HPP waned, and China Export & Credit Insurance Corporation’s (Sinosure) interest in providing insurance to the lenders diminished”.


The letter disclosed that some previous potential investors had backed out, forcing the sponsors to seek new financing options.


Given that the project is situated in AJK, where there is “a notable disinterest among lenders”, the company required additional time to secure alternative funding sources.


Currently, the CTG is tasked with securing $2.5 billion in financing and obtaining insurance coverage from Sinosure, hence the push for a three-year extension.


Moreover, the Chinese side has also raised “several outstanding key issues, with technical, financial, and environmental implications,” which must be addressed before achieving financial closure.


It said the company needed 8,600 kanals of land for the project, of which 4,607 kanals had already been acquired under the Land Acquisition Act, 1894.


Since the AJK government notified a new Land Acquisition Act in 2020 and new rules in 2021, the letter sought confirmation that the remaining land for the project would be purchased under the old law.


It also complained that the Nepra had “not honoured ECC decisions related to Sewage Treat­ment Plants and foreign exchange Losses/Gains in excess of 7pc on delayed payment”.


The company said despite adverse macroeconomic conditions, it remai­ned “steadfastly committed to advancing the project”. Therefore, it demanded an extension in LoS and a financial closing deadline of Sept 2027.


Published in Dawn, June 1st, 2024


http://dlvr.it/T7gvG5

Comments

Popular posts from this blog

Pragmatic steps taken to implement Axle Load Control regime on NH&MP

Islamabad: Ministry of Communications has taken pragmatic steps to implement the Axle Load Control regime on Motorways & National Highways in the country. Sole objective of this move is to control travelling of overloaded vehicles which lead to fatal accidents besides damaging the national asset of road network of billions of rupees.Prior to implementation of axle load control regime, a technical committee was formed, consisting of officers from Ministry of Communications and National Highway Authority which remained in constant contacts with transport community, Members of the Chambers of Commerce and stakeholders hailing from all the provinces. This technical committee visited their offices and held detailed discussions in series of meetings and took them into confidence to facilitate implementation of Axle Load Control regime. The stakeholders assured of their full cooperation and subsequently, implementation of Axle Load Control was realized which is in progress.It is worth to ...

CJP questions how ‘clarification order’ made it to website

ISLAMABAD: Chief Justice of Pakistan (CJP) Qazi Faez Isa has raised nine questions in a letter to the Supreme Court’s registrar, seeking clarification on how a Sept 14 clarification order was uploaded to the top court’s website. The Sept 14 order, issued by eight judges led by senior puisne judge Justice Syed Mansoor Ali Shah, criticised the Election Commission of Pakistan (ECP) for failing to implement the Supreme Court’s July 12 judgement, which declared the PTI eligible for reserved seats in parliament. In his letter dated Sept 21, the CJP wondered who directed the uploading of the Sept 14 clarification order on the Supreme Court’s website. His inquiry followed a note from the Deputy Registrar (Judicial), who flagged the issue of the order’s appearance on the website. The note questioned how the order was uploaded when no cause list had been issued, no notices had been sent to the parties, and the order had not been received by the deputy registrar’s office until 8pm on the...

UN awards 2 Pakistani female peacekeepers for gender advocacy

The United Nations has awarded two Pakistani female peacekeepers with the Gender Advocacy Award for their “outstanding performance”, a statement from the Inter-Services Public Relations (ISPR) said. In a statement issued on Thursday, the ISPR said the awards were presented to Major Sania Safdar, part of the UN Peacekeeping Mission in Cyprus, and Major Komal Masood, who served in the Central African Republic, “for their outstanding performance and commitment in promoting the ideals of UN”. The accolades were presented by the under-secretary general in the UN’s Department for Peace Operations at its New York headquarters. “While serving in [an] international environment, both officers demonstrated exceptional professionalism [and] dedication,” the ISPR noted. It added that the two peacekeepers “made [a] significant contribution to Mission’s Peace and Stability efforts, especially with regards to advancing women’s meaningful participation in Peacekeeping Operations within the ...