Anomalies detected in execution of Rs1bn education project in KP

PESHAWAR: Provincial Inspection Team (PIT), Khyber Pakhtunkhwa, has detected drastic ‘illegalities’ in the execution of Rs1 billion project meant for providing early childhood education material and furniture to government primary schools.


PIT has recommended necessary action against the senior officials at directorate of elementary and secondary education department for committing illegalities in awarding contract and release of the whole payment to the contractors prior to completion of the project.


The illegalities declared in the inquiry report include ‘issuance of illegal early childhood education (ECE) completion certificates to the contractors and releasing full payment in advance ie before June 30 2022’.


PIT has also recommended necessary action against the members of procurement committee for committing several illegalities including approval of the contractors, who were not fulfilling the minimum eligibility criteria. The report of inspection team said that one of the contractors was declared the best bidder for supply of furniture despite the fact that an FIR was already registered against him.



Inquiry report recommends action against senior officials at directorate of elementary and secondary education



Besides officials at directorate level, it has also recommended that disciplinary action may be taken against the then district education officers (male and female) of Peshawar and Bannu for releasing payment to contractors without obtaining inspection reports from the relevant committee constituted on January 28, 2022, for the purpose. It resulted in substandard, below specification and incomplete supply of furniture, said the inquiry report.


“The elementary and secondary education department may be further directed to constitute a similar committee to confirm and verify all the procured ECE material in terms of quality, quantity and specification and take appropriate action accordingly,” it said.








The probe committee said that the contractors selected for supply of furniture were not qualified because they did not have an authentic proof of registered factory and required level of capital and revenue as mentioned in the technical criteria and hence the award was unlawful for which the procurement committee was responsible.


The probe committee also inspected the supplied furniture in Peshawar and Bannu and found that the end users (schools) expressed dissatisfaction over the quality of furniture, which was broken and below specification.


The report said that the then district education officers did not obtain inspection and completion reports from the inspection committee constituted by education department and released payments to furniture contractors.


The purchase committee constituted for purchase of ECE material awarded contracts to those contractors, who were found ineligible for having no authentic proof of registered factory, authorisation of original manufacturer and required level of working capital/revenue as mentioned in the technical criteria.


The inquiry committee found that the contractors had not completed the supply of ECE material timely as per their agreement with the directorate of education department but the directorate unlawfully released all the payments to them in advance and issued completion certificate to them.


While probing the procedures, the inquiry committee found that the officials responsible for dealing the matter at directorate level were quite dubious as initially they presented a certificate to PIT that the ECE supply was completed.


However, when PIT approached the district level formation of education department for confirmation of supplied furniture, it was found that the supply of ECE was incomplete. After this exercise, the officials presented a new agreement to PIT wherein they had extended the deadline from June 30, 2022, to April 30, 2023.


Similarly, the officials at directorate issued a letter to drowning and disbursement officer (DDO) for release of fund and said that performance guarantee from all contractors was collected by the directorate but on record no authentic performance guarantees of banks were received by the directorate from contractors and instead performance bonds of an insurance company were obtained by the officials which was unlawful.


The secretary of elementary and secondary education department, Mutasim Billah was not available for comments.


Published in Dawn, November 27th, 2023


http://dlvr.it/SzNnS6

Comments

Popular posts from this blog

3 drug pushers, bootlegger held

Islamabad :Islamabad Industrial Area Police have arrested three drug pushers and a bootlegger besides recovery of narcotics and 120 liter liquor from them, a police spokesman said.According to details, a police team of Industrial Area police station arrested three drug pushers namely Kamran, Irfan and Shamoon Masih and recovered 320 gram heroin and 210 gram hashish from them,.Another police team arrested a bootlegger namely Ansar Javed and recovered 120 liter wine, bottles, stickers and brewing equipment from him. Cases have been registered against these nabbed persons and further investigation is underway from them.SP (Industrial Area) Zubair Ahmad Shaikh has said that Industrial Area zone police is doing its job efficiently and crackdown against criminals would be continued.Despite the sit in, he said Islamabad Police has been performing its duty quite efficiently and has successfully managed to maintain the daily life in the Capital.In this regard, Senior Police officers including S...

‘Aziz Bhatti Shaheed My Brother, My Hero’

Real heroes are heroes of every one. They are not controversial. Nations love them more than anything. Major Aziz Bhatti Shaheed is among those real-time heroes of 1965 War, who not only stood firm to face the enemy aggression but also repulsed it with his unprecedented courage. He gave his life while defending the frontiers of motherland but never let the enemy succeed in its nefarious designs. The proud nation awarded him with ‘Nishan-i-Haider’, the biggest gallantry award of the country. Now that more than 54 years have passed, since he embraced Shahadat, he continues to live in the hearts of each and every Pakistani. Aziz Bhatti is remembered with love and affection. Nation observes his Yaum-e-Shahadat on 12th of September in a befitting manner.This year was significant in a sense that his younger brother Sardar Ahmed Bhatti (95 years old now) presented this nation a book named ‘Aziz Bhatti Shaheed My Brother My Hero’. This book is classic and unique in a way that it unearths many ...

Pragmatic steps taken to implement Axle Load Control regime on NH&MP

Islamabad: Ministry of Communications has taken pragmatic steps to implement the Axle Load Control regime on Motorways & National Highways in the country. Sole objective of this move is to control travelling of overloaded vehicles which lead to fatal accidents besides damaging the national asset of road network of billions of rupees.Prior to implementation of axle load control regime, a technical committee was formed, consisting of officers from Ministry of Communications and National Highway Authority which remained in constant contacts with transport community, Members of the Chambers of Commerce and stakeholders hailing from all the provinces. This technical committee visited their offices and held detailed discussions in series of meetings and took them into confidence to facilitate implementation of Axle Load Control regime. The stakeholders assured of their full cooperation and subsequently, implementation of Axle Load Control was realized which is in progress.It is worth to ...