PESHAWAR: The flagship project of the Pakistan Tehreek-e-Insaf (PTI) government in Khyber Pakhtunkhwa, the Peshawar Sustainable Bus Rapid Transit (BRT) Corridor Project, is set to miss the June 30 deadline proposed by National Economic Council (NEC) as only 61 percent of work on the project has been completed thus far.The BRT project, which has become an irritant for the government and source of criticism for the opposition, was started in 2017. Addressing the groundbreaking ceremony of the project on October 19 that year, Chief Minister Pervez Khattak pledged to complete the ambitious project in six months.However, the PC-I of the project clearly indicated April 2021 for its completion. The chief minister stuck to their pledge of completing the project in six months even when it looked impossible to do so. Around eight deadlines were given for completing the project as a fresh one had to be announced every time. The official deadline of June 30, 2019 was conveyed through a letter in N...